Last week , Sleepy Hollow Road construction crews continued to make progress on the following activities:
-Removed and replaced a section of damaged sidewalk across from Westfield Community School.
-Continued landscape restoration throughout the entire project area
-Continued installing railing and decking on the boardwalk near Barrett Drive
-Completed installation of the boardwalk bracing, which gives the structure extra support
-Cleaned up around the boardwalk work area
This week , crews will continue working on pedestrian, bike and roadway improvements, including:
-Boardwalk railing and decking installation to create a safe walkway for pedestrians.
-Paving the northern and southern sections of the bicycle path (from Wynnfield Drive north to County Line Road and from Longmeadow Parkway south to Grandview Drive, respectively).
-Landscape restoration throughout the entire project area.