Last week, crews made great progress and completed mainline sewer installation up to the north side of Fox 14 Marina. The contractor will continue progressing north from the marina next week and we anticipate that the sewer will be completed in the next few weeks.
Once the mainline sewer is complete, crews will resume work completing the remaining service connections, storm sewer improvements and water service replacements.
A special property access notice:
All residents south of Fox 14 Marina should access their properties from Front Street or Algonquin Road, including properties along Park Street, Brook Street, Riverview Drive and Fox 14 Marina.
All residents north of Fox 14 Marina should continue to follow the detour and access their properties from Blackhawk Trail.