(From Public Works) Last week, crews completed the mainline sewer installation along the 600 block of North Harrison Street. Crews also completed pavement patching on Edwards Street and started pavement patching along North Harrison Street between Edwards Street and Sunny Drive.
Due to the holidays, the contractor will not be performing any work between Dec. 22 and Jan. 1.
Two way traffic has been restored for those within the work area. Drivers should proceed with caution as North Harrison Street remains a construction zone.
Work and the detour will resume along North Harrison Street on Jan. 2, starting at the intersection of Park Street and progressing north along the 700 block of North Harrison Street.
Detour Alert
The Stage 2 detour has been temporarily lifted through Jan.1, 2020. The detour will be restored on Jan. 2 and is expected to remain in place for several weeks. North Riverview Drive between North Main and Park streets will be closed as part of the Stage 2 detour. Access to residences and businesses within the work zone will be maintained.