Construction Update (from Public Works)

This week, crews restored the roadway at the intersection of Algonquin Road and Main Street and reopened it to traffic. On La Fox River Drive, the construction team continued installing the final sanitary sewer service laterals* and removed the temporary dewatering wells.

Next week, ComEd will relocate utilities at the intersection of Washington and Harrison streets. Our crews will work to complete the sewer and water main installation from the north side of Crystal Creek to Algonquin Road.

At the end of the week, crews will begin removing curb, sidewalk and driveway aprons** along La Fox River Drive as they prepare to replace them. Crews will provide temporary gravel ramps so residents can maintain access to their driveways.

http://oldtownalgonquin.org/stage-3-south-harrison-street...

*The pipe connecting a residence or business to the main sewer line.

**The approach where the road and driveway meet.