This week, trail users were directed back onto the new ramp! Crews also finished installing the final pieces of the block retaining wall, regraded the slope along the bridge sides and removed the temporary ramp.
Next week, the construction team will prepare the bridge deck (surface). Crews will also focus on other parts of the project, including:
Beginning electrical preparation for installing the bollard lamps along part of the Trail (visit the project website to learn more about the lamps). https://oldtownalgonquin.org/old-town-prairie-trail.html
Installing brick pavers near the new pergola.
Thank you for your patience and cooperation as we near the end of construction!