Public Works Construction Update

Downtown Algonquin construction Items completed last week:

Finished placing the retaining wall along RT 31 by the lift station wet well.

Completed water main pressure testing and chlorination.

Disconnected the electrical service and relocated the street lighting at the River Front Lift Station at the intersection of N. Harrison and Front streets.

Here are the contractor's plans for next week:

Conclude all underground water main work within the roadway on La Fox River Drive and Center Street, which includes the following:

Finish connecting the final two water mains to the existing water main.

Complete installation of water services.

Complete removal and abandonment of the River Front Lift Station.

Have the control building for the lift station delivered and set on the building foundation.

Pour the concrete pad* of the odor control system for the lift station.

*Base on which the unit will sit

Detours and Closures:

La Fox River Drive between RT 31 and Center Street as well as Center Street north of La Fox River Drive remain closed.