Terrace Hill Roadway Rehab Project Update

The Terrace Hill Roadway Rehabilitation Project (from Public Works) - The project is moving ahead and making great progress. This week crews installed:
Sanitary sewers on Persimmon Drive
Storm sewers on Greens View Drive

On Monday, crews will wrap up the sanitary sewer point repair on Persimmon Drive and spend the rest of the week working on the storm sewer. Crews will also continue working on Greens View Drive storm sewers, north of Bunker Hill Drive. Construction crews will notify residents if their driveway will be directly impacted by construction.
If you have questions or concerns, please contact Doug Paulus, Project Engineer via email (DougPaulus@algonquin.org) or by phone 847-658-2754 ext. 4403.

Thank you in advance for your patience and interest in this project.