Water/Sewer Work Update

Water/Sewer Work Update (from Public Works) - Last week, crews installed the mainline sewer up to 925 North Harrison Street. The mainline sewer work is nearing completion. The contractor also completed the replacement of water and sewer services on the 600 block of North Harrison Street and began replacements along the 700 block of North Harrison Street. Road patching continued along the 500 block of North Harrison Street as the underground work was completed.

This week, the contractor will continue replacing water and sewer services along the 700 and 800 blocks of North Harrison Street. Crews hope to also be able to continue working on storm sewer replacements in this same area of North Harrison Street. This work may include construction within the intersection of Park and North Harrison streets. Crews expect to continue with road patching work as well.

As the Stage 2 Harrison Street Project nears completion, the Village would like to thank you for your patience and cooperation during construction.

A special property access notice:

All residents south of Fox 14 Marina should access their properties from Front Street or Algonquin Road, including properties along Park Street, Brook Street, Riverview Drive and Fox 14 Marina.
All residents north of Fox 14 Marina should continue to follow the detour and access their properties from Blackhawk Trail.
Please be advised that while crews are working on water and sanitary service connections and storm sewer replacement on the 700 and 800 blocks of North Harrison Street, residents within the work area may need to follow the Stage 2 detour temporarily during working hours. Residents will have full access during off hours.