Construction Update (from Public Works):

This week, crews completed the demolition of the existing Riverfront Lift Station just north of Port Edwards. As weather permits, the following work will be completed:

-The masonry contractor will place the exterior brick on the Generator Control Building.

-The electrical contractor will install the final equipment associated with the Lift Station and the Generator Control Building, this work will continue for the next few weeks.

The contractor anticipates initial startup and testing of the Lift Station and Generator Control Building to be in the beginning of March.