Downtown Algonquin Construction Update (from Public Works):

The previous cold weather impacted progress on the work related to the Generator Control Building. During this time, crews focused on the electrical work inside the building. This week, the rising temperatures allowed the crews to resume brick work on the building. The contractor is also coordinating with both the gas and power utility companies to finalize service installations. After service is installed, the contractor will perform the initial startup and equipment testing.